Call us on telephone icon 01226 785 722

News

21st November 2022

Guided Auger Boring 3 Stage Installation Process

We have now completed our project in #Bridlington installing Naylor Industries PLC DN150 #clay #drainagepipe using the #guidedaugerboring 3 stage installation process.
1 – Install the steerable pilot rod to line, level and grade using our OEN system.
2.) Ream up to size, removing spoil from the cutting head back to the launch pit using the reusable casing and auger
3.) Install the DN150 clay jacking pipe through to the reception pit and complete the drive
to see a detailed 3D animation of this process
Follow Trenchless Solutions Ltd to see more up and coming projects !!

Share



Filter by Division

Archive

Accreditations

  • Acclaim Accreditation

  • Achilles UVDB Verified

  • Constructionline Gold

  • SSIP

  • UKSTT